CONSTRUCTION

Here are our live webcams for the construction site of Tour des Canadiens 2 & Tour des Canadiens 3. Check back regularly for updates!

image
June 2019
Work on Place Jean D’Estrées has officially begun. In the next few weeks, you will see many trades getting down to work.

May 2019
The canopy structure at the entrance of the Tour des Canadiens 2 is now installed! The final result is almost ready.The canopy structure at the entrance of the Tour des Canadiens 2 is now installed! The final result is almost ready.
April 2019
The construction hoist on the east side of Tour des Canadiens 2 will be removed. This will allow us to start the landscaping work of the future Plaza Jean-D’Estrées.
March 2019
We can proudly see the three (3) townhouses on Torrance Street. When Spring arrives, work on the green roof will begin.
February 2019
Without a doubt, the Passerelle now connects the Tour des Canadiens 2 to the Deloitte Tower. You can admire its structure from St-Antoine Street. Work is progressing at a good pace.
January 2019
Have you noticed that the Montreal Canadiens logos were delivered to the top of the Tower? The installation is scheduled for Spring 2019!
December 2018
It is time for the transition between the idea on paper and the reality that construction brings. The Bridge will have its steel skeleton attached to Tour des Canadiens 2 and Deloitte Tower for further work to occur. Congratulations to the entire team for such a great coordination!
November 2018
Have you noticed the big drill between the Bell Center and Deloitte Tower? If so, you have witnessed the beginning of the installation of the pillars of the future bridge connecting Tour des Canadiens 2 to the RESO.
October 2018
At the dawn of winter, we are finalizing the landscaping work on the south side of Tour des Canadiens 2. From the paving stones to potted plants and planted trees, everything will be ready for next spring.
September 2018
Finishing touches are being made in the common areas of Tour des Canadiens 2 : measurements for the curtains, installation of the lights fixtures, ordering the furniture and testing the mechanical equipment. Gradually, we can imagine the residents there living beautiful moments.
August 2018
It’s the return from the construction holidays for the workers. The site is active and resumes its cruising speed to optimize the beautiful weeks of the summer that remain.
July 2018
The reconstitution of the historic facade on Saint-Antoine Street is almost finalized. It is a perfect symbiosis of history and modernity. We invite you to take a glance!
June 2018
Have you noticed that we have started to close the 54th floor of Tour des Canadiens 2? This will allow us to work in the main mechanical rooms of the building. These rooms will require several weeks of work to be completed.
May 2018
Work is underway in the common areas. The pool area has its ceramic installed. The wooden floor is being laid down in the wine bar. Finally, the fitness room takes shape with its white brick wall accent.
April 2018
The window-wall installation is advancing at a great pace. We have reached the 26th floor. On average, our team manages to complete one floor per week, depending on the weather.
March 2018
Topping off Tour des Canadiens 2 has happened!
We are proud to have completed all concrete slabs and reached the maximum height of the structure. We have achieved this goal in record time.
November 2017
We take to heart the quality of our construction as well as the future quality of life of the owners. In fact, we will be performing many tests as construction progresses. For example, acoustic tests of the party walls will be conducted during the month of November to ensure an optimal rendering to the customers.
October 2017
We began the installation of the curtain wall for the Atrium of Tour des Canadiens 2. The installation process of the glass facade is progressing at a good pace. We receive additional glass panels every week at the construction site.
September 2017
We have started to make appointments with the future owners of TCD2 for them to make the final choices on the color of the finishes in their unit. Each owner will be presented with a choice of 3 color packages. Stay tuned!
image
June 2019
The installation of the curtain wall of the facade on St-Antoine Street is progressing: Insulation, glass, finishing touches. The whole team is working in unison to make everything watertight as quickly as possible.
May 2019
The 30th floor concrete slab was poured. The structure is progressing at an unprecedented pace. Congratulations to all the team for their excellent coordination.
April 2019
In Tour des Canadiens 3, things are moving at a high speed: Installation of plumbing and electrical, various ventilation systems, sprinklers, etc.
March 2019
The installation of the window-wall for Tour des Canadiens 3 has now begun. The team plans to install 1 floor per 7 days of work in average, depending on weather conditions. Follow their progress for the next few months.
February 2019
The first segment of the construction hoist has been installed on the south side of Tour des Canadiens 3. This will facilitate the transportation of materials to different floors and accelerate the work progress.
January 2019
Winter holidays are over. The Tour des Canadiens 3 construction can now resume.
December 2018
It’s official, Tour des Canadiens 3 is now above ground! Work on the 4 garage floors will be happening in warm conditions, while the Tower will continue to gain height.
November 2018
More and more concrete trucks are coming to the Tour des Canadiens 3! The concrete pours are made more quickly. The big question: which floor will we be on before the Christmas construction holiday?
October 2018
Pedestrian protection has been installed on De la Montagne Street and St-Antoine West. With the start of the hockey season and the growing number of pedestrians, it was essential for the safety of people.
September 2018
Did you know …? There is at least one meeting per week between the general contractor, the architect, the mechanical engineer, the structural engineer and all the subcontractors to coordinate each concrete pour. This is the perfect time for everyone to discuss the logistics of the work.
August 2018
All things come in threes! The third crane is installed on the site of Tour des Canadiens 3. This allows more materials to be moved and an increase in the speed of the work.
July 2018
The second crane is now installed and functional. The site will thus advance twice faster!
June 2018
The first TDC3 project crane was installed on site, which means that work for the concrete pours can now be coordinated. In priority, we will cast the elevator pit and the structural columns.
May 2018
And here we are, we have reached the lowest point of TDC3. An arduous work of excavation that lasted several weeks is now completed. Congratulations to the team!
April 2018
The soil excavation at Tour des Canadiens 3 is progressing. We are on the 3rd basement level. In average, there are between 25 to 30 trucks per day in charge of bringing the soil into the dumping site.
March 2018
Official launch of the Tour des Canadiens 3!
It is with great joy that we made our launch of construction of the Tour des Canadiens3.
A 55-storey building in the heart of downtown Montreal.