CONSTRUCTION

Here are our live webcams for the construction site of Tour des Canadiens 2 & Tour des Canadiens 3. Check back regularly for updates!

image
July 2018
The reconstitution of the historic facade on Saint-Antoine Street is almost finalized. It is a perfect symbiosis of history and modernity. We invite you to take a glance!
June 2018
Have you noticed that we have started to close the 54th floor of Tour des Canadiens 2? This will allow us to work in the main mechanical rooms of the building. These rooms will require several weeks of work to be completed.
May 2018
Work is underway in the common areas. The pool area has its ceramic installed. The wooden floor is being laid down in the wine bar. Finally, the fitness room takes shape with its white brick wall accent.
April 2018
The window-wall installation is advancing at a great pace. We have reached the 26th floor. On average, our team manages to complete one floor per week, depending on the weather.
March 2018
Topping off Tour des Canadiens 2 has happened!
We are proud to have completed all concrete slabs and reached the maximum height of the structure. We have achieved this goal in record time.
November 2017
We take to heart the quality of our construction as well as the future quality of life of the owners. In fact, we will be performing many tests as construction progresses. For example, acoustic tests of the party walls will be conducted during the month of November to ensure an optimal rendering to the customers.
October 2017
We began the installation of the curtain wall for the Atrium of Tour des Canadiens 2. The installation process of the glass facade is progressing at a good pace. We receive additional glass panels every week at the construction site.
September 2017
We have started to make appointments with the future owners of TCD2 for them to make the final choices on the color of the finishes in their unit. Each owner will be presented with a choice of 3 color packages. Stay tuned!
image
July 2018
The second crane is now installed and functional. The site will thus advance twice faster!
June 2018
The first TDC3 project crane was installed on site, which means that work for the concrete pours can now be coordinated. In priority, we will cast the elevator pit and the structural columns.
May 2018
And here we are, we have reached the lowest point of TDC3. An arduous work of excavation that lasted several weeks is now completed. Congratulations to the team!
April 2018
The soil excavation at Tour des Canadiens 3 is progressing. We are on the 3rd basement level. In average, there are between 25 to 30 trucks per day in charge of bringing the soil into the dumping site.
March 2018
Official launch of the Tour des Canadiens 3!
It is with great joy that we made our launch of construction of the Tour des Canadiens3.
A 55-storey building in the heart of downtown Montreal.